– Preparation of Environmental Impact Assessment (EIA) study;
– Preparation of Social Impact Assessment study;
– Technical aspects of infrastructure project with focus on licensing and all planning aspects under Albanian zoning law;
– Technical study of dam Spathara strength;
– Data mining;
– Land expropriation plan;
– Analysis and monitoring of the permitting status,
– Support to the collection of permits and authorizations necessary for Project development, construction and commissioning;
– Examination of the existing permits for the local use of water resources that may affect the technical requirements, Project timeline and bankability;
– Project risk analysis, including approaches for mitigating technical and operational risks, delays, government approval/permitting issues, off-take agreement, cost overrun, management and financial risks
– Support in public relations.