Task 1: Development of PIU operating procedures
Project Implementation Plan (PIP);
Administrative procedures;
The project implementation schedule;
The monitoring and quality assurance procedures.
Task 2: Support during the procurement process
The technical approach is based on the following key factors and preconditions:
a) Erection of new substations and substation extension projects need a detailed, careful and comprehensive site inspection.
b) A scope of work can only be defined in close cooperation with client’s staff, i. e. specialists and operational staff c) All necessary steps for an Environmental and Social Impact Analysis (ESIA) and the Environmental and Social Action Plan (ESAP) will be considered during the planning phase of the transmission line and substation works to respond to local regulations and requirements and international practices.
d) Tender documents prepared in a clear and comprehensive manner that
The preparation the Environmental and Social Impact Analysis (ESIA) and the Environmental and Social Action Plan (ESAP) are integral components of the project
Task 3: Support during the evaluation process
Stage 1: Evaluation of Post Qualification Documents
Stage 2: Technical Evaluation
Stage 3: Financial Evaluation of bids
Task 4: Support during contract finalization